TENTATIVE Construction Schedule

Warwick Township 2017 Road Program (Bray Brothers, Inc.)

Monday, July 10, 2017

  • Meyer Way- sidewalk/ ADA ramps replaced
  • Starting Tar & Chip – Colony Rd, Park Dr., Meadowview Dr., & Wayne Dr.
  • Storm Pipe crossing installation on Watson Rd. at Rushland Rd. (PW employees)

Monday, July 17, 2017

Road Patching Will Begin on all Roads in the 2017 Program

Meyer Way

Deer Run Road ( Route 263 to Doe Court)

Fallow Hill Lane (Deer Run to Mill Road)

Eddowes Road

Mulberry Lane

Robinwood Drive

Persimmon Lane

Valley View Drive

Chelsea Lane

Long Pond Drive ( Valley View Drive to Bristol Rd)

Hedgewood Drive

Rosewood Lane

East Rockspray

Primrose Court

Oleander Court

North & South Daisey Drives

Thyme Court

Wisteria Circle

Ironwood Drive

Arrowhead Circle

Dogwood Drive (E Rockspray to the walking path)

Monday August 7, 2017

Milling of all roads on the above list will begin starting with Meyer Way

Monday August 21, 2017

Paving of all roads on the above list will begin starting with Meyer Way