Progress this Week on Warwick’s 2017 Road Program

Scheduled work has been delayed due to rainy weather and the holiday. Bray Brother’s is continuing the paving of Long Pond Drive, Persimmon Lane, Valley View Dr, Chelsea Lane, Rosewood Ln & Hedgewood Dr. Completion is scheduled in the next two weeks. On approximately Monday, 9/25, milling, pavement repair and paving will begin on Eddowes Road.

 

Schedule for Remaining Work on the Warwick Township’s 2017 Road Program

Bray Brother’s is quickly working to complete the road program. Currently they are in Hidden Ponds completing milling and patching on Long Pond Dr, Persimmon Lane, Valley View Dr, Chelsea Ln, Rosewood Ln, & Hedgewood Dr. Paving is scheduled to start next week. 

Work will continue to the following roads when paving in Hidden Ponds is completed:

Eddowes Rd

E. Rockspray

Primrose Court

Oleander Court

N Daisey

S Daisey

Wisteria Circle

Ironwood Drive

Thyme Court

Arrowood Circle

Dogwood Drive (E Rockspray to the walking path)