Water Main Break on Stony Road

A water main broke this morning on Stony Road at Mayfield Circle between Meyer Way and Turkeytrot Road.  Crews are working to repair the break.  Vehicular access has been restored to Mayfield Circle.

A large volume of water has flooded this area.  The roads are salted, however; ice is still likely due to the temperatures.  Use caution.

As of 4:30pm – Water has been restored.

School Road Bridge Update

The developer for the Warwick Mill residential development has been reconstructing the School Road bridge and road since the beginning of 2017.  The bridge is nearing completion with only a guiderail left to be installed.

Originally scheduled for November 17th, the installation of the guiderail was delayed due to the contractor’s schedule.  The developer has confirmed the dates of December 1st to the 8th as the tentative guiderail installation dates.  Assuming the installation is completed on schedule, School Road and the bridge should be reopened to vehicular traffic thereafter.  Thank you for your patience.

Route 263 Update 11-9-17

                While the major reconstruction is substantially complete, work remaining includes smoothing, painting, adding reflectors, grading, and some work at the bridge valley bridge.  There will be some lane diversions and the project anticipated completion is years end.  We appreciate everyone’s patience.

 

Route 263 Update 11-6-17

Rout 263 update – crews are out to complete work at intersections with Stover Mill and Heritage Creek.  If materials arrive before it rains, it will be completed today.  If not, it will be completed shortly when weather cooperates. 

 

Route 263 Update 10-31-17

Please note that although the major part of the project is complete you will still see some short term lane closures to finalize grading, and some additional added work. These items could not be started until the paving was complete. PennDOT expects to be fully complete by the end of November, weather permitting.

 

Memorial Park- Warwick Township’s Newest Park- Construction Update 10/17/2017

Memorial Park (Phase #1) is close to completion. The parking lot and driveway are scheduled to begin paving this week.

Memorial Park is located at 1200 Memorial Drive, which is just inside the entrance to the new Toll Brothers development, The Woodlands at Warwick. Please remember that this is a construction site and is NOT OPEN to the public! No trespassing is permitted. We will announce when it will be open to the public. Please watch for more updates on Facebook and the Warwick Township website!